When did you last stop for the light at Westlake Drive on Loop 360? For anyone heading straight through, it was late August. On Sunday, August 30, the Texas Department of Transportation opened a new mainlane in each direction that lets drivers skip the signals at both Westlake Drive and Cedar Street. KXAN reported the opening two days ahead of time.
The Westlake Drive and Cedar Street project started in June 2022. Its connector roads, bridges and paths are still being built, and the final paving and striping that will make the new layout permanent come last. Meanwhile, the next Loop 360 project has already started just north of the river. Its expected finish is late 2029, roughly three years after Westlake's. Over the next few years, a Westlake commute toward northwest Austin will run past more construction across the river than at home.
TxDOT's project page lays out the temporary pattern drivers use today.
This is what the project was designed to do. Drivers going to Cedar Street or Westlake Drive turn off at the side, and through traffic heading for the river keeps moving. In a May 2026 Loop 360 guide, a TxDOT spokesperson told the Austin American-Statesman that traffic studies show most Loop 360 traffic is through traffic. Removing the stoplights and moving turning cars out of the main lanes should keep it flowing.
The current pattern is single lanes and temporary routing, so overnight lane and access closures on the connector roads between Bold Ruler Way and the Pennybacker Bridge still happen. TxDOT posts them on the project page, and they change week to week.
TxDOT splits the project into five phases. The bypass lanes opened before the earlier phases were done, so most of the list is still in progress.
| Phase | Work | Status on TxDOT's project page |
|---|---|---|
| 1 | Set up the work zone, build waterlines | Complete |
| 2 | New northbound and southbound connector roads, drainage, shared-use paths | Ongoing |
| 3 | Westlake Drive bridge, begin the new mainlanes | Ongoing |
| 4 | Cedar Street bridge, complete the mainlanes | Ongoing |
| 5 | Final paving and striping, open the permanent traffic patterns | Upcoming |
TxDOT expects completion in "late 2026, weather permitting." In June 2025, TxDOT's construction information sheet forecast mid-2026, so the date has already moved once. Community Impact's October 30 transportation roundup still lists the late-2026 target. It says construction on the mainlanes between Bold Ruler Way and the Pennybacker Bridge continues through the end of the year.
Phase 5 matters to residents because "permanent traffic patterns" are the layout you will actually live with. That includes final lane striping, final connector road alignments and the full set of mainlanes. Until then, the single bypass lane in each direction is a temporary setup. TxDOT's posted rules for when crews can work also hint at what remains. Excavation runs weekdays from 7 a.m. to 7 p.m. and Saturdays from 9 a.m. to 3 p.m., and hauling happens at night.
The work at home cost $72.1 million and began in June 2022. KUT reported when work started that $14 million of the funding came from the City of Austin's $720 million mobility bond, approved by voters in 2016. The contractor is Copasa Group.
The new bridges carry more than car lanes. TxDOT's 2019 design boards show three pieces for people walking and biking:
The paths were not built at full width everywhere. KUT reported in 2022 that the plans narrowed the path in some spots along Loop 360's east side. In places it shrinks to 8 feet, with a 2-foot buffer where it runs beside the cliffs and the right-turn lanes at Westlake Drive. On a weekend walk or ride, those tighter stretches are where you will pass oncoming bikes most closely. The shared-use paths are part of Phase 2, which is still ongoing.
As the Westlake work winds down, the next project picks up on the other side of the Pennybacker Bridge. At Courtyard Drive and RM 2222, TxDOT is taking the signal off the Loop 360 mainlanes again. This time it is building an underpass at Courtyard Drive and turning the RM 2222 interchange into a diverging diamond. Crews broke ground on April 29, 2026, according to Community Impact.
The two projects side by side:
| Westlake Drive / Cedar Street | Courtyard Drive / RM 2222 | |
|---|---|---|
| Construction start | June 2022 | April 2026 |
| Expected completion | Late 2026 | Late 2029 |
| Cost | $72.1 million | $68.4 million |
| What changes | Signals removed, mainlanes dropped beneath Westlake Drive and Cedar Street | Signal removed with an underpass at Courtyard Drive, diverging diamond at RM 2222 |
| Paths | Shared-use paths and sidewalks | Shared-use paths and sidewalks |
The schedule follows the same pattern as Westlake's. The Statesman's construction guide explains that the Courtyard bridge comes first. Next is the diverging diamond at RM 2222. Final paving and striping come last, followed by the opening of the permanent traffic patterns.
The bridge between the two projects stays as it is. The Pennybacker Bridge has crossed the Colorado River since 1982, and the plans make no changes to it. It will remain two lanes in each direction.
One change near the bridge hits weekend plans more than commutes. The same Statesman guide reported TxDOT's plan to put up barriers near the trail to the Pennybacker Bridge overlook as crews set up the Courtyard work zone. With the barriers in place, cars can no longer park at the trailhead. TxDOT said the boat ramp near the bridge would stay open.
Beyond Courtyard, the next Loop 360 projects depend on funding more than on construction schedules:
For Westlake households, the last two projects are closest to home. Walsh Tarlton, Westbank Drive and the Bee Cave Road interchange are all on the south side of the river. None of them has a construction date, so the Courtyard Drive zone north of the Pennybacker Bridge is the only Loop 360 construction with a firm calendar after Westlake Drive and Cedar Street wrap up. TxDOT's Loop 360 project pages remain the place to check closures each week until the final striping is done.
Infrastructure timelines like these affect how a home is priced, and Cord pays close attention to what is changing on Loop 360, from Cedar Street to Courtyard Drive. If you're weighing a move on either side of the Pennybacker, or want to know how the finished interchange may affect a property you own, Cord Shiflet Group can walk you through it. Work with Cord.
Stay up to date on the latest real estate trends.
Relocation
Relocation
Cord prizes trust. His clients trust him to value and protect their real estate investments. And how’s this for a bonus? He is fun to work with because he loves his work. Whether representing an A-list celebrity or Austin executive, Cord personifies Texas’ entrepreneurial spirit: Play hard. Have fun. Work harder.